The City of Jeffersonville 2025 Paving Season has begun!
Below you will find updates on where the City is working this season. This page will be updated frequently. Keep in mind, roadwork is weather permitting.
Monay, October 13 – Friday, October 17 – Milling and Paving
- Springdale Drive (8th Street to Optimist Avenue)
- Spring Street (E. 10th Street to 14th Street)
Milling anticipated to take up to 2 days, paving will follow
Monday, September 8 – Friday, September 12 – Milling and Paving
- Walnut Street (Riverside Drive to E. Market Street)
- E. Market Street (Pearl Street to Jackson Street)
- Wall Street (E. Market Street to 240′ SE of E Market Street floodwall)
Milling anticipated to take 2-3 days, paving will follow
Wednesday, August 13 – Milling
- Burning Tree Court (St. Andrews Road to end)
- St. Andrews Road (Augusta Drive to Charlestown Pike)
Thursday, August 14 – Paving
- Burning Tree Court (St. Andrews Road to end)
- St. Andrews Road (Augusta Drive to Charlestown Pike)
Thursday, August 14 – Milling
- E. 11th Street (Main Street to Penn Street)
- Walnut Street (E. Court Avenue to E. 7th Street)
Friday, August 15 – Paving
- E. 11th Street (Main Street to Penn Street)
- Walnut Street (E. Court Avenue to E. 7th Street)
Friday, August 15 – Milling
- Evergreen Circle (800′ E of Charlestown Pike to 3416 Evergreen Circle – Full loop to SE)
- Emerald Court (Childers Dr. to West End – 400′ W. of Childers Drive)
Monday, August 18 – Paving
- Evergreen Circle (800′ E of Charlestown Pike to 3416 Evergreen Circle – Full loop to SE)
- Emerald Court (Childers Dr. to West End – 400′ W. of Childers Drive)
Monday, August 18 – Milling
- Grandview Drive (Linden Road to 400′ SE of Linden Road)
- Rosewood Drive (McBride) (Allison Lane to Linden Road)
- Graceland Way (Rosewood Drive – McBride Drive to Grandview Drive)
Tuesday, August 19 – Paving
- Grandview Drive (Linden Road to 400′ SE of Linden Road)
- Rosewood Drive (McBride) (Allison Lane to Linden Road)
- Graceland Way (Rosewood Drive – McBride Drive to Grandview Drive)
Monday, July 28 – Milling
- Bitter Sweet Road (Pampaw Drive to Hawthorne Drive)
- Utica Pike (Six Mile Lane to 215′ N of Six Mile Lane – Bridge Seam)
Tuesday, July 29 – Milling
- Utica-Sellersburg (New Chapel Road to Sundancer)
- Vissing Park Road [Wilcox] (E. 10th Street to 1000′ NW of Windmill Lane)
Wednesday, July 30 – Milling
- Slone Drive (Kirk Lane to 280′ SE of Hampton Drive – 4504 Slone Drive)
- Dunbar Drive (Scott Drive to East End – 500′ NE of Kevin Court)
- Crums Lane (Hamburg Pike to Scott Drive)
Wednesday, July 30 – Thursday, July 31 – Paving
- Bitter Sweet Road (Pampaw Drive to Hawthorne Drive)
- Utica Pike (Six Mile Lane to 215′ N of Six Mile Lane – Bridge Seam)
Thursday, August 1 – Friday, August 2 – Paving
- Utica-Sellersburg (New Chapel Road to Sundancer)
- Vissing Park Road [Wilcox] (E. 10th Street to 1000′ NW of Windmill Lane)
- Bitter Sweet Road (Pampaw Drive to Hawthorne Drive)
- Utica Pike (Six Mile Lane to 215′ N of Six Mile Lane – Bridge Seam)
Tuesday, July 8 – Milling
- Presidential Place (Middle Road to Blueberry Way)
Tuesday, July 8 – Milling
- Presidential Place (Middle Road to Blueberry Way)
Wednesday, July 9 – Milling
- Apache Drive (Seminole Drive (600′ E of Allison Lane) to Seminole Drive (200′ E of 4 Way)
- Seminole Drive (Allison Lane to Apache Drive (2250′ NE of Allison Lane)
Wednesday, July 9 – Paving (may take 1-2 days)
- Presidential Place (Middle Road to Blueberry Way)
Thursday, July 10 – Milling
- Crystal Springs Blvd (Boulder Ridge Drive to Mackenzie Drive)
- Crystal Lake Drive (380′ N of Crystal Springs Blvd. to N ide of Regency Way)
- Boulder Ridge Way (Brookhollow Way to 120′ N of Horse Trail Road)
Thursday, July 10 – Paving (may take 1-2 days)
- Apache Drive (Seminole Drive (600′ E of Allison Lane) to Seminole Drive (200′ E of 4 Way)
- Seminole Drive (Allison Lane to Apache Drive (2250′ NE of Allison Lane)
Friday, July 11 – Paving (may take 1-2 days)
- Crystal Springs Blvd (Boulder Ridge Drive to Mackenzie Drive)
- Crystal Lake Drive (380′ N of Crystal Springs Blvd. to N side of Regency Way)
- Boulder Ridge Way (Brookhollow Way to 120′ N of Horse Trail Road)
Friday, June 20 – Milling
- New Middle Court (New Middle Road to Middle Road)
- Middle Road (New Middle Court to Utica-Sellersburg Road)
- Utica-Sellersburg Road (Middle Road to Pinewood Drive)
Monday, June 23 – Paving (may take 1-2 days)
- New Middle Court (New Middle Road to Middle Road)
- Middle Road (New Middle Court to Utica-Sellersburg Road)
- Utica-Sellersburg Road (Middle Road to Pinewood Drive)
Monday, June 23 – Milling
- Peach Blossom Drive (Holmans Lane to Orchard Hills Drive)
- Snyder Drive (Thompson Lane to Northaven Drive)
Tuesday, June 24 – Paving (may take 1-2 days)
- Peach Blossom Drive (Holmans Lane to Orchard Hills Drive)
- Snyder Drive (Thompson Lane to Northaven Drive)
Tuesday, June 24 – Milling
- Northaven Drive (Snyder Drive to Ruck Lane)
- Woodland Road (E. 10th Street to Aster Road)
Wednesday, June 25 – Paving (may take 1-2 days)
- Northaven Drive (Snyder Drive to Ruck Lane)
- Woodland Road (E. 10th Street to Aster Road)
• Thursday, May 22 – Milling Woodland Court from Woodland Road to Cardinal Lane
• Friday, May 23 – Paving Woodland Court from Woodland Road to Cardinal Lane
- Monday, April 21 – Pave 7th Street
- Tuesday, April 22 – Pave Basswood & Blackwood
- Wednesday, April 23 – Pave Darien & Elder
- Thursday, April 24 – Pave Fulton Street
- Monday, April 7 – Wednesday, April 16
- Woodland Ct road closure for road improvements
- Will close off road Monday morning with proper detour route set up to reroute traffic
- Tuesday, April 8
- Mill
- Stonelilly Dr
- Robin Ln / Robin Rd
- Mill
- Wednesday, April 9
- Mill
- Brim Dr
- Plaza Dr
- Royal Oaks Way
- Mill
- Thursday, April 10
- Pave
- Stonelilly Dr
- Robin Ln / Robin Rd
- Pave
- Friday, April 11
- Pave
- Brim Dr
- Plaza Dr
- Royal Oaks Way
- Pave